GS Breaks Ground on 15 Trillion Won Donghae AI Data Center... Aims to Bring 1.2 GW Online by 2029
- Input
- 2026-11-28 12:24:43
- Updated
- 2026-11-28 12:24:43

[Financial News] GS Group has launched the first phase of a 15 trillion won project to build an artificial intelligence (AI) data center in Donghae, Gangwon Province. It is the first GW-scale AI data center included in the government’s “South Korea’s 3 Mega Projects,” announced in June, to break ground. GS plans to begin by completing its first 100-megawatt (MW) data center in June 2028, then build and bring online facilities with a total capacity of 1.2 GW by 2029. GS Group said it held a groundbreaking ceremony for the Donghae GS AI Data Center on the 28th at the Bukpyeong 2nd General Industrial Complex in Donghae, Gangwon Special Self-Governing Province, attended by President Lee Jae-myung and GS Group Chairman Huh Tae-soo, among others.
GS is pursuing its 2.4 GW AI data center project in two phases of 1.2 GW each. The first phase will involve building data centers with a combined capacity of 700 MW across three sections of the Bukpyeong 2nd General Industrial Complex, as well as a 500 MW facility on an additional site.
The 100 MW facility for which construction began today is targeted for completion in June 2028. Construction of the 200 MW and 400 MW facilities is scheduled to begin in the first half of next year, with completion by the end of 2028. The remaining 500 MW facility is targeted for completion in 2029.
GS announced last September that its phase-one investment would be approximately 15 trillion won. The cost of building the full 2.4 GW of facilities is estimated at approximately 30 trillion won. GS projected that the overall project could be worth as much as 120 trillion won, including equipment costs for graphics processing units (GPUs), memory and other components.
After establishing its dedicated subsidiary, GS AI Infra, last June, GS signed a memorandum of understanding with Gangwon Special Self-Governing Province and Donghae City in July to develop the data center. It passed the final review of the power system impact assessment last August and obtained a building permit for the first 100 MW facility in October.
GS is also working with LS ELECTRIC Co., Ltd., POSCO, LG Uplus and Honeywell Technologies on data center equipment procurement, design and operations.
GS has formed a mutual growth and development council with Donghae City and is also developing plans to expand local employment and gather residents’ opinions. GS estimates that the first-phase project will require a cumulative total of about 70,000 people during construction and about 1,000 direct and indirect workers during operations.
In his welcoming remarks today, Chairman Huh said, “By building AI data centers, we will expand the foundation of Korea’s AI industry, create local jobs and increase opportunities for companies to participate.”