Vietnam State Audit Says Lotte’s Thu Thiem Eco Smart City Should Be Charged an Additional 189 Billion Won in Land Fees
- Input
- 2026-11-27 22:34:16
- Updated
- 2026-11-27 22:34:16

According to local media on the 27th, Vietnam’s State Audit Office said in its report on the results of the 2025 audit of Ho Chi Minh City’s local budget, published last month, that some of the underlying data used in the detailed land-price calculation for Lotte’s Thu Thiem Eco Smart City project were problematic.
Specifically, the audit office found indications that some banks had provided interest rates that differed from actual levels in connection with the discount rate used to calculate land prices. VietinBank submitted a rate of 11.083%, while Vietnam Petroleum Bank submitted 11.325%. But after rechecking the figures against actual average interest rates in 2021–2022, the audit office calculated an appropriate discount rate of 9.175%.
In particular, an analysis found that if only the discount rate recalculated by the audit office were applied, while leaving the other variables in the previously approved land-price calculation unchanged, the land-use fee the project operator would have to pay into the state budget would increase by at least VND 3.647 trillion (about 189 billion won).
The report also said that some apartment transaction price data provided by Ho Chi Minh City’s Land Registration Office for land valuation lacked credibility. In one case, the information-provision confirmation was stamped October 19, 2022, while the attached notarized contract was dated earlier, on June 20, 2022.
Concerns were also raised about social housing obligations. The project’s total residential land area is 24,090.3 square meters, of which 20%, or 4,818.1 square meters, must be set aside for social housing under the regulations. The audit office said the documents submitted so far were insufficient to verify how the project operator had fulfilled its social housing obligations or the results, and provisionally estimated the payment corresponding to the value of technical infrastructure investment on the designated social housing site at VND 13 billion (about 673.9 million won).
Accordingly, Vietnam’s State Audit Office recommended that the Ho Chi Minh City People’s Committee have relevant specialized agencies comprehensively review the sale price data used to calculate development profits for Lotte Eco Smart City, and have the chairperson of the Ho Chi Minh City People’s Committee report a proposal to reapprove the specific land price and recalculate financial obligations under the relevant regulations. It also called for measures requiring the project operator to pay an amount equivalent to the value of infrastructure investment on the land allocated for social housing.