Transfer Checks Completed for Nuri (KSLV-II) 1st-, 2nd-, and 3rd-Stage Mockups Ahead of the 6th Launch
- Input
- 2026-11-26 10:45:02
- Updated
- 2026-11-26 10:46:25

[Financial News] Nuri has completed checks on the transport of its launch vehicle assemblies ahead of its sixth launch next year.
The Korea AeroSpace Administration and the Korea Aerospace Research Institute said on the 26th that they had completed advance checks of land and sea transport procedures in Suncheon from the 24th to the 26th, together with Hanwha Aerospace, Nuri’s systems integration company, using mockups of its first, second, and third stages.
Up through Nuri’s fifth launch, assembly of the individual stages and final assembly had been carried out at the Naro Space Center in Goheung. Starting with the sixth launch, however, the plan is to assemble the first, second, and third stages separately at Hanwha’s Suncheon plant, transport each completed stage by land and sea to the Naro Space Center, and then carry out final assembly of the launch vehicle in preparation for launch. The checks were conducted in advance to confirm that the transport equipment and procedures were suitable, using mockups of the first, second, and third stages before transporting the actual stage assemblies for Nuri No. 6.
The transport checks took place on a land route connecting the stage assembly facility in Suncheon and Yulchon Pier, and on a sea route from Yulchon Pier to waters near Dolsan Island. The team checked the process of securing the mockups to dedicated transport fixtures, moving them with a self-propelled modular transporter (SPMT), and loading them onto a barge. The actual Nuri stage assemblies are planned to be transported about 121 km from Yulchon Pier to the Naro Space Center. During these checks, the team traveled a round trip of about 80 km from Yulchon Pier to waters off Dolsan Island while inspecting the transport process.
The Korea Aerospace Research Institute drew on experience transporting launch vehicles gained during development of Naro-1 (Korea Space Launch Vehicle-1, KSLV-1) in planning this transport operation. Based on its experience bringing the first stage of Naro-1, built in Russia, to Korea by air and then transporting it over land and sea to the Naro Space Center, the institute provided technical advice on securing methods, transport equipment, and routes for safe transport. Hanwha incorporated that advice to develop the stage mockups and transport fixtures and establish the transport procedures.
In these transport checks, Hanwha oversaw the land and sea transport of the stage mockups, while the Korea AeroSpace Administration and the Korea Aerospace Research Institute jointly reviewed the transport process and procedures on site. Based on the results, the administration, the institute, and Hanwha plan to proceed smoothly with transporting each stage of Nuri No. 6 and work together to ensure the new transport procedures operate reliably.
“Even the safe transport of a launch vehicle requires technology built up through years of development and operational experience,” said Lee Sang-cheol, president of the Korea Aerospace Research Institute. “We will work closely with Hanwha Aerospace to make thorough preparations for transporting the actual stages.”
“Since stage assembly for Nuri No. 6 will take place at the stage assembly facility in Suncheon, advance checks of land and sea transport procedures are important,” said Korea AeroSpace Administration chief Oh Tae-seok. “We will carefully manage every stage of the transport process to ensure the stage assemblies can be moved safely and make every effort to keep preparations for next year’s sixth launch on track.”
[email protected] Yeon Ji-an Reporter