Vietnam’s North–South Express Railway Project Sets Schedule, Targets Construction Start in Late 2028
- Input
- 2026-11-25 16:06:33
- Updated
- 2026-11-25 16:06:33

【Hanoi, Vietnam—Kim Jun-seok, correspondent】Four key milestones have been set for consulting services on Vietnam’s North–South express railway project, a massive national project with a total cost of $67.3 billion (about 95 trillion won). On the 21st, Korea National Railway, Yushin, Sambo and others won the contract as part of a global consortium formed with companies from France, Vietnam and other countries. They will be responsible for the railway’s feasibility study and basic design. Vietnamese authorities aim to begin main construction in late 2028, following a 30-month feasibility study and basic design process.
According to local media reports on the 25th, the Thang Long Project Management Board, under the Ministry of Construction and the client for the North–South express railway project, said it had established four major milestones for the 30-month consulting contract, covering field surveys, preparation of the feasibility study report, front-end engineering design (FEED), and preparation of bidding documents.
The consulting consortium must complete a proposal on the technical standards to be applied to the project and the basic design requirements within three months of the contract. It must submit an interim report within 13 months covering alternative routes, the locations of major hubs and the selection of the optimal technology. In the 27th month, the feasibility study report will be submitted to the review committee and Vietnam’s Ministry of Construction for review. The schedule calls for final approval from the relevant authorities in the 30th and final month.
The client plans to conduct intensive, detailed topographical and geological surveys along the entire route from the first through the third quarter of next year. It also plans to prioritize completing documents that finalize site boundaries so local governments can begin land compensation, assistance and resettlement procedures within 2027. Vietnamese authorities plan to carry out this roadmap without delays and begin construction in late 2028.
Earlier, on the 20th, the Thang Long Project Management Board officially approved the award decision for the “TV-02 Package,” which covers surveys for the North–South express railway, preparation of the feasibility study report, FEED and preparation of bidding documents. The winning bidder is a multinational consortium of eight companies from South Korea, France and Vietnam. The winning bid was about 10.2 trillion dong (about 560 billion won), and the contract period is 30 months. The consortium includes three South Korean companies—Korea National Railway (KR), Sambo Engineering and Yushin—as well as France’s SYSTRA and four Vietnamese companies: TEDI, TEDI SOUTH, TRICC and Hoang Long Construction Consultancy.
The Thang Long Project Management Board is currently negotiating detailed contract terms with the winning consortium and plans to sign the main contract by the end of this month. The contract will specify each consortium member’s responsibilities, as well as plans to train specialized personnel at local Vietnamese engineering institutions, transfer technology and hand over calculation software.
The North–South express railway will span 1,541 km, connecting Ngoc Hoi Station in Hanoi with Thu Thiem Station in Ho Chi Minh City and passing through 15 Vietnamese provinces and cities. It will be a double-track railway using standard gauge (a track gauge of 1,435 mm), with a design speed of 350 km/h and an axle load of 22.5 tonnes. The total project cost is provisionally estimated at about $67.3 billion (about 95 trillion won).