[Financial News] LS Cable & System has won a project to expand the transmission capacity of the subsea power grid linking Haenam County in South Jeolla Province and Anjwado Island in Sinan County. The plan is to support the expansion of renewable energy in the southwestern coastal region by installing additional subsea cables in partnership with LS Marine Solution.
LS Cable & System said on the 20th that it had been selected as the contractor in competitive bidding for the “Hwawon-Anjwa Subsea Cable Capacity Expansion Phase 2 Construction Project,” commissioned by Korea Electric Power Corporation (KEPCO).
The project will add a total of 14 km of 154-kV extra-high-voltage subsea cable to the subsea power grid between Hwawon-myeon in Haenam County and Anjwado Island in Sinan County, built in 2010. LS Marine Solution’s 9,000-ton-class subsea cable-laying vessel GL2030 will be deployed, with completion targeted for December 2028.
The Hwawon-Anjwa subsea power grid was the first project LS Cable & System participated in after it became the first company in Korea to localize extra-high-voltage subsea cable production in 2009. After winning the first capacity expansion project in 2021, it has now won the second phase as well. In effect, the company will continue to take on follow-up projects on the same route, from the initial grid construction through two capacity expansions.
The two companies are also expanding their businesses in high-voltage direct current (HVDC) subsea cables. LS Marine Solution is building a 19,000-ton-class HVDC subsea cable-laying vessel, aiming to put it into service in 2028. LS Cable & System plans to combine its experience commercializing HVDC subsea cables with LS Marine Solution’s construction capabilities to participate in national power grid projects, including the West Coast Energy Expressway.
A representative of LS Cable & System said, “For subsea cables, proven quality and a track record of execution in actual power grids are important,” adding, “We will strengthen our market leadership based on the technological expertise we have built since becoming the first in Korea to localize production, together with LS Marine Solution’s construction capabilities.”