LH: “If Orders for 3,000 or More Modular Homes Are Bundled, Construction Costs Could Fall to RC Levels”
- Input
- 2026-11-20 11:09:48
- Updated
- 2026-11-20 11:09:48

[Financial News] Korea Land and Housing Corporation (LH) is considering a plan to lower construction costs to levels comparable to reinforced concrete (RC) construction by bundling orders for modular housing on a large scale.
According to LH on the 20th, the corporation held a forum on building a stable ecosystem for modular housing at its Seoul Regional Headquarters on the 19th. Attendees included LH President Lee Seong-hoon, the head of its Public Housing Division and other LH officials, as well as industry and academic experts from Samsung C&T, GS E&C, NRB, and Ewha Womans University. The forum followed a meeting with modular housing manufacturers held on the 3rd. It was organized to swiftly implement the government's “8·13 Housing Rapid Supply Plan” and to address technical and institutional issues in the field through cooperation among the public sector, private sector, and academia.
The discussion focused on costs. LH unveiled a cost-cutting roadmap that takes its “volume-price linkage system” a step further. The discussion included a plan to reduce construction costs further, to RC levels, on top of existing cost-cutting targets, if orders for 3,000 or 5,000 or more homes are bundled into integrated packages.
The volume of orders starts at 2,200 homes this year. LH said it would announce its mid- to long-term ordering schedule in advance. The aim is to make the business environment more predictable so private companies can achieve break-even utilization rates at their factories and invest in research and development (R&D) and automated equipment.
Ways to shorten construction periods were also discussed. LH decided to accelerate demonstrations of ultra-high-rise modular housing. It also explored ways to switch the core sections, which had previously been built using cast-in-place methods, to dry construction, in order to shorten the overall construction period as much as possible.
The industry and academic experts who attended said large-scale integrated orders and a mid- to long-term supply roadmap would attract investment. They said these measures would help accelerate construction companies' and modular housing specialists' investment in automated mass-production lines, as well as the commercialization of ultra-high-rise and dry-construction technologies, and expressed their willingness to cooperate. Lee Jun-seong, a professor at Ewha Womans University, said, “For the modular housing industry to continue to grow, creating a predictable business environment and maintaining consistent communication with the industry are more important than anything else.” He added, “I hope this forum will lead to more active cooperation and communication among the public sector, private sector, and academia, and help strengthen the competitiveness of the industry as a whole.”
The government and LH have recently raised their modular housing order targets in succession. Under its 8·13 measures, the government raised the target for orders of modular public housing from 12,000 to 20,000 homes for 2027–2030. It also decided to launch a pilot project for modular housing of 20 stories or more. On the 3rd, LH held a meeting with six manufacturers—NRB, Plan M, Yoochang, Kumkang Kind, Daeseung Engineering, and XiGEIST—and said it would order at least 3,000 homes annually from next year through 2030, focusing on 3rd Generation New Towns in the Seoul metropolitan area. That is 2,000 more than the target of 16,000 homes announced last month. The volume of orders for next year is set at 3,500 homes or more. LH also changed how production costs are paid: instead of paying progress payments after modules arrive at the site, it will make payments in line with the progress of factory production.
However, ensuring project viability remains a challenge. LH's first modular housing project put out to tender this year, in Seongju Seongju District, for 100 homes, failed to attract a private-sector bidder. Critics say that although modular construction can shorten construction periods, high manufacturing and transportation costs make it difficult to ensure a project's viability. This is seen as the reason LH is emphasizing cost reductions this time.
The president said, “As modular housing has become more important for rapidly expanding housing supply, stable growth in the related industry will directly lead to increased capacity to supply homes.” He added, “We will bring together the capabilities of the public sector, private sector, and academia to remove obstacles to the industry's growth and actively support efforts to deliver tangible results in housing supply.”
[email protected] Jeong Gyeong-su Reporter