LH to Cut Time from Procurement to Construction Start from 130 to 63 Days, Pursue Emergency Bidding and Streamlined Procedures
- Input
- 2026-11-19 09:23:09
- Updated
- 2026-11-19 09:23:09

LH said on the 19th that it had drawn up and would implement a plan to expedite procurement, contracting and construction starts in line with the government’s “8.13 Housing Fast Supply Plan.”
First, LH will shift from managing schedules with a focus on signing contracts to working backward from the actual planned construction start date to set procurement schedules. It will strengthen prior consultations between the procurement department and the departments responsible for contracts and reviews, and use emergency bidding for projects that need to be procured urgently.
For construction projects worth at least 30 billion won that are subject to the comprehensive evaluation-based bidding system, LH will cut 67 days from the period between procurement planning and construction start. Annual planning will allow it to skip advance publication of procurement plans. It will also omit site briefings, reducing the time for site briefings and quotations from 34 days to two days. The schedules for prequalification (PQ) and comprehensive evaluation will also be shortened.
LH plans to consult with contractors and carry out contract signing and construction preparations in parallel, so that construction can begin as soon as the relevant procedures are complete. Advance reviews of procurement requests and advance notice of construction plans will also help reduce delays caused by failed bids, corrections and re-announcements.
The procedural improvements will also apply to projects worth less than 30 billion won. LH aims to shorten the timeline for projects worth at least 10 billion but less than 30 billion won that are subject to the simplified comprehensive evaluation-based bidding system from 105 days to 57 days, and for projects under 10 billion won subject to qualification reviews from 98 days to 43 days. It also plans to use emergency bidding for technical services such as surveying and appraisal, and general services such as research and project support.
LH has also reached an agreement to use emergency bidding when necessary for public housing design, construction and supervision work transferred to the Public Procurement Service (PPS). It has completed requests to procure through emergency bidding all 38 projects scheduled to start construction this year, worth about 5.4 trillion won in total.
President Lee Seong-hoon said, “We will innovate processes throughout procurement, contracting and construction, start housing projects earlier, and deliver housing-supply results that people can feel.”