Gwangju Centennial IPARK Completes Pre-Occupancy Inspection Amid Praise From Prospective Residents; Completion Set for Late December
- Input
- 2026-11-17 15:07:09
- Updated
- 2026-11-17 15:07:09

[Financial News] IPARK Hyundai Development Company has completed the pre-occupancy inspection of Gwangju Centennial IPARK, which it rebuilt from the ground up.
According to IPARK Hyundai Development Company on the 17th, it held a pre-occupancy inspection event for prospective residents of Gwangju Centennial IPARK over two days, the 14th and 15th.
Gwangju Centennial IPARK is a residential complex being built on a site in the area of 23-27 Hwajeong-dong, Seo District, Gwangju, Jeonnam-Gwangju Integrated Special City. It will comprise seven buildings, with four basement levels and up to 39 floors above ground, and a total of 847 households. The existing buildings were completely demolished and rebuilt, and completion is expected at the end of December this year.
Prospective residents checked the interior finishes in the units and the shared facilities. Amid a positive atmosphere, some prospective residents also put up banners at the complex entrances and on fences to express their gratitude for the company’s fulfillment of promises made during construction.
IPARK Hyundai Development Company plans to carefully review the items that customers asked it to check during the pre-occupancy inspection and address them promptly before move-in.
Lee Seung-yeop, a representative of the prospective residents, said, "Judging by the messages posted in the group chat after people looked around the homes, most seem satisfied." He added, "Since this is a complex we completed together after working hard, some people also told the contractor that it had worked hard throughout the process."
During the reconstruction of Gwangju Centennial IPARK, IPARK Hyundai Development Company further strengthened its on-site safety and quality management systems to ease the concerns of customers who had signed contracts and improve construction quality.
First, it increased the concrete design strength from the previous 27 MPa to 30 MPa. It conducted sampling inspections starting when ready-mixed concrete arrived at the site and introduced a real-name quality accountability system that records the names of managers and workers on major structural work. The entire construction process was also recorded on video and retained.
It also conducted quality verification involving outside experts. The company formed a Construction Innovation Task Force that included Professor Park Hong-geun of Seoul National University's Department of Architecture and others, and carried out regular inspections. It also took measures to strengthen on-site safety management, including establishing a chief safety officer organization and guaranteeing workers the right to stop work.
A dedicated organization was also run to support prospective residents during the reconstruction. The A1 Task Force was stationed at the site to share updates on the reconstruction and gather residents' requests. Support measures, including interest-free loans for housing support expenses, were implemented, and the project also incorporated upgrades to interior finishing materials in the units and specialized landscaping and community facilities.
A representative of IPARK Hyundai Development Company said, "We are deeply grateful to the prospective residents who trusted us and waited for a long time, as well as to local residents who showed consideration for the inconvenience caused during construction." The representative added, "Having honored our commitments with safety and quality as our top priorities, we will fulfill our responsibilities to the end to ensure that move-ins are completed without disruption following completion at the end of December."
[email protected] Choi A-young Reporter