Chuncheon secures 23.9 billion won in national funding for water and sewer projects; Yongsan Water Treatment Plant construction to be completed next February
- Input
- 2026-11-10 10:26:33
- Updated
- 2026-11-10 10:26:33

【Financial News, Chuncheon = Kim Gi-seop, Staff】Chuncheon's Yongsan Water Treatment Plant modernization project will be completed next February, and the city's water infrastructure will undergo a major overhaul, including the installation of new pipelines in rural villages that have not had access to piped water.
According to Chuncheon City on the 10th, the city has secured 23.9 billion won in national funding and 6.5 billion won in provincial funding for major water and sewer projects next year. The city will use the funds to upgrade aging water supply systems, address areas with limited access to water, modernize wastewater treatment facilities, and expand sewer services in rural areas.
The largest project is the 84.9 billion won modernization of Yongsan Water Treatment Plant. The project involves building a new plant with a capacity of 30,000 tons per day and laying 7.1 km of conveyance and transmission pipelines. Construction will be completed next February, followed by trial operations. A new project to lay 40 km of water mains in and around Otan-ri and Goseong-ri in Sabuk-myeon will get underway at a cost of 13.6 billion won. Work will also continue to expand water supply facilities in other villages without piped water, including Jichon-ri in Sabuk-myeon and Joyang-ri in Dongsan-myeon.
In the city center, aging water supply networks will be replaced in stages. The work will cover 18.2 km in and around Soyang-dong and Yaksamyeong-dong, and 18.5 km in and around Hyoja-dong and Hupyeong-dong. The goal is to reduce leaks and rusty water and improve supply efficiency.
In the sewer sector, a project to relocate and modernize the public wastewater treatment facility in Geunhwa-dong to Chiljeon-dong is ongoing. The city is also upgrading a water reuse facility capable of reusing 16,000 tons of treated water per day, along with 9.2 km of supply pipelines. In rural areas, it will lay 11.7 km of new sewer lines and install drainage facilities at 283 sites in and around Wolsong-ri in Seomyeon, Songam-ri in Sabuk-myeon, and Jeung-ri in Sindong-myeon.
Sewer construction in rural and fishing villages in and around Jiam-ri in Sabuk-myeon, Daritgol in Namsan-myeon, and Wonchang-ri in Dongsan-myeon will also continue. In the city center, the city plans to upgrade major sewer lines, including the Uiam sub-basin, Janghak trunk line, and Gangchon sub-basin, to strengthen its wastewater treatment infrastructure.
A Chuncheon City official said, “Once construction of Yongsan Water Treatment Plant is completed next February, we will be able to produce 30,000 tons of tap water per day more reliably,” adding, “We will continue to expand infrastructure so that people in both urban areas with aging water networks and rural villages without piped water can live without worrying about water.”
[email protected] Kim Gi-seop Reporter