"Speed Up the Quynh Lap LNG Power Plant Project"... Nghệ An Province Urges SK Innovation Consortium

Input
2026-09-18 17:29:19
Updated
2026-09-18 17:29:19
A meeting held on the 17th to review progress on the Quynh Lap LNG Power Plant Project, attended by the leadership of Nghệ An Province, the SK Innovation·PV Power·NASU Sugar Company investment consortium, and relevant government departments. Provided by the Nghệ An provincial government.
【HANOI, Vietnam—Kim Jun-seok, Correspondent】Authorities in Nghệ An Province have asked the SK Innovation·PV Power·NASU Sugar Company consortium and relevant agencies to expedite the construction of the Quynh Lap liquefied natural gas (LNG) combined-cycle power plant. The project is a major large-scale power initiative, with a planned generation capacity of 1,500 MW and a total investment of $2.2 billion.
According to local media on the 18th, Phung Thanh Binh, vice chairman of the People’s Committee of Nghệ An Province, held a meeting on the 17th with representatives of the investment consortium and officials from relevant departments and agencies. They focused on ways to accelerate the Quynh Lap LNG power plant project and resolve problems arising during the land acquisition process, including site clearance.
The SK Innovation·PV Power·NASU Sugar Company investment consortium said that it had officially established Quynh Lap LNG Power Company, the project company, on the 14th. The independent company will directly operate the Quynh Lap LNG power plant project, creating a foundation for it to make advance payments for site clearance costs.
Nghệ An Province emphasized that it aims to complete the formal contract signing this month.
The Department of Finance also said, "We are providing guidance on the relevant procedures so that the project company can make advance payments for site clearance compensation to local authorities." The advance payments will later be deducted from the project’s land payments in accordance with the 2024 Land Law.
Vice Chairman Binh praised the efforts of the investor and the relevant departments and agencies, while asking the investment consortium to sign a site clearance agreement with local authorities by the 25th.
Vice Chairman Binh also instructed the Department of Industry and Trade to work with the Department of Finance and the investment consortium to finalize a detailed schedule for the project. Key milestones include approval of the feasibility study (FS) report, approval of the 1:500 detailed plan, completion of the environmental impact assessment, the start of construction, and the construction schedule.