Monday, November 23, 2026

[Exclusive] Construction Costs Rise Despite 'Reduction Recommendations'... An On-Site Look

Input
2026-09-10 14:20:08
Updated
2026-09-10 14:20:08
Yonhap News
Trend in Construction-Cost Reduction Recommendations Issued by the Korea Real Estate Board
[Financial News]#. A redevelopment project site in Eunpyeong District, Seoul. In the third quarter of 2024, it received verification from the Korea Real Estate Board (KREB) that a construction-cost increase of 165.6 billion won was appropriate. The amount initially submitted for verification was 186.6 billion won, meaning 11.3% of the total was cut.However, in the first quarter of the following year, 2025, the association agreed with its existing contractor to a contract raising construction costs by approximately 250 billion won. That was about 100 billion won more than the amount verified by KREB.Most redevelopment project sites that applied to KREB for construction-cost verification received recommendations to reduce their costs. Yet sites that signed contracts at higher amounts are also readily found, because there are no legal penalties or other regulations for failing to follow the verification results.
At some sites, associations and contractors have agreed to exploit the verification process. Criticism is growing that the system has effectively degenerated into a sham measure.
■Reduction Recommendations Are Increasing, but What Is Happening on Site?According to a comprehensive review by Financial News on the 10th, KREB recommended reducing construction costs by a total of 4.701 trillion won through verification of redevelopment project sites over the past five years. The amount has increased every year.
It was only 430 billion won in 2022, but rose steadily to 646.1 billion won in 2023, 791.3 billion won in 2024 and 1.7214 trillion won in 2025. This year, it had already surpassed 1 trillion won, reaching 1.1122 trillion won as of August.
Judging by the figures alone, the system appears effective. But an entirely different story is emerging on the ground.
Because there are no legal penalties for failing to implement the recommendations, many do not follow them. In some cases, associations and contractors even apply for verification at an amount higher than actually needed, anticipating the reduction that will be recommended.
Project B, located in the three Gangnam districts (Gangnam, Seocho and Songpa) of Seoul, is one such case. Project B is a so-called large-scale complex with several thousand households, and it was highly popular from the time it was offered for sale.
The association and contractor for the complex have agreed to construction-cost increases at least three times so far. During this process, they added the anticipated reduction to the amount needed and submitted that higher figure to KREB for verification. For example, if 100 billion won were needed for a construction-cost increase, they would apply for verification of 110 billion or 120 billion won, factoring in an anticipated reduction of 10% to 20%.
Project B used this method to secure the full amount of construction costs it needed. An official in the construction industry said, "If the contractor and association agree, there is no way to identify such cases. The fact that this workaround is already being used openly shows that the system has many loopholes."
■Seoul Accounts for Only 30%... Other Regions Make Up the Remaining 70%Because construction-cost verification is conducted nationwide, similar cases are likely to be even more common. KREB verified 179 sites over the past five years, of which 55 were in Seoul—only about 30%.
The remaining 70% is concentrated in other parts of the Seoul metropolitan area and other regions, including 41 sites in Gyeonggi Province, 21 in Busan, and 13 each in Incheon Metropolitan City and Daejeon. There are also numerous projects in each region where the amount subject to construction-cost verification exceeds several hundred billion won.
That is why calls are growing for the system to be overhauled quickly. A real estate expert who requested anonymity said, "This year alone, redevelopment projects worth more than 4 trillion won have undergone construction-cost verification by KREB. With many redevelopment projects scheduled nationwide, including those in Apgujeong, Yeouido, Mokdong and Seongsu-dong, we need to address the loopholes in the current system."
[email protected] Kwon Jun-ho Reporter