[Financial News] The Lee Jae-myung administration has officially begun reviewing plans to build new nuclear power plants and extend the permitted period for continued operation. The move is aimed at ensuring a stable power supply for the Yongin and Honam semiconductor clusters.
On the 24th, the Ministry of Climate, Energy and Environment told Rep. Na Kyung-won of the People Power Party, a member of the National Assembly Committee on Climate, Energy, Environment and Labor, in a written response that it would discuss new nuclear plant construction and an extension of the continued-operation period.
Earlier, Climate Minister Kim Seong-hwan had raised the need for new nuclear plants and a longer continued-operation period to supply power to semiconductor clusters. The ministry’s response to the National Assembly made clear that the government has now formally entered the review process.
Review of new nuclear plants for Honam power shortages
In response to a question about whether the construction of two new nuclear plants in Honam is being considered in the revision of the 12th Basic Plan for Long-term Electricity Supply and Demand, the ministry said, "The construction of new nuclear plants will take into account electricity supply and demand needs, construction schedules, local acceptance, and the suitability of nuclear plant sites." It added, "During the formulation of the basic plan, we will comprehensively review whether to include new nuclear plants by considering the views of experts, stakeholders, and the public."
For the Honam semiconductor cluster, it has already been pointed out that the power output of the six Hanbit Nuclear Power Plant units would not be enough to run the four fabs previously known to be planned. With reports that two more fabs are now under review, observers say new nuclear plant construction has become unavoidable. For that reason, Minister Kim Seong-hwan and even Song Young-gil of the ruling Democratic Party of Korea (DPK) have argued that new nuclear plants are needed.
The ministry said the revised plan will soon be released in draft form, then go through a public hearing, a strategic environmental impact assessment, and a climate change impact assessment before being submitted to the National Assembly. Whether new nuclear plants will be included is expected to become clear when the draft is announced.
Discussion with NSSC and KHNP on a 20-year continued-operation period
The ministry said it will discuss extending the permitted period for continued operation of nuclear plants with the Nuclear Safety and Security Commission (NSSC) and Korea Hydro & Nuclear Power (KHNP). In response to a question asking about its review plan for extending the current 10-year limit to 20 years, and the ministry’s position on the matter, it said, "We will consult with the NSSC and KHNP on which continued-operation period for nuclear plants would be more reasonable."
It also said it would "review the need for stable power supply," suggesting that the move is intended to prepare for a sharp rise in electricity demand from the development of the Yongin and Honam semiconductor clusters.
The proposal to extend the continued-operation period was originally made directly by Rep. Na to Minister Kim. On the 11th, Na suggested at the committee that the period be extended from the current 10 years to 20 years, and that it be calculated from the expiration date of the design life to effectively lengthen operating time. Minister Kim said, "We will review which is more reasonable, 10 years or 20 years."
The permitted period for continued operation is based on the Enforcement Decree of the Nuclear Safety Act. The Nuclear Safety Act delegates detailed matters on operating permits to a presidential decree, and Article 36 of the enforcement decree defines the "expiration date of the design life" as the first expiration date and the date 10 years after that. This means the extension can be made by revising the enforcement decree alone.